Quick acceptance kitchen and bathroom coup

A lot of people in the renovation acceptance, the bathroom and kitchen acceptance is not careful enough, after living for some time and found that the bathroom sewer is always blocked, leaking, the kitchen exhaust pipe is not very smooth, these problems not only bring the owners of life Inconvenience, it is to add to the owner's heart. If it was good to have a kitchen inspection, how good would it be, but unfortunately no! So, how should the kitchen bathroom be accepted?

Quick acceptance kitchen and bathroom coup

Before entering the gate, you need to prepare a “Residential Quality Assurance Certificate,” “House Use Instruction,” and “Completion Acceptance Record Form.” Check whether the housing condition is consistent with the developer’s commitment to the quality of the house and the warranty period and scope.

Check whether the toilet is blocked: fill the floor with water and check for leaks. In housing quality complaints, leakage, ventilation and other issues are relatively large. Therefore, the inspection and acceptance of toilets must be very careful.

Acceptance method for kitchen and bathroom:

Check the ventilation of the bathroom. Check if there is a vent reserved under the ceiling. If it is left on the ceiling, check with a flashlight to see if it has installability. Test the pumping force and check the toilet vent for construction waste with a flashlight. The bathroom is in the corridor. Windows should be equipped with security nets. If there are no windows, ventilation holes should be installed. The vent hole is 10 cm in diameter and is located below the suspended ceiling; the distance from the nearest outlet to the ventilation hole should be.

Kitchen, bathroom acceptance method II:

Check the quality of toilets and baths in the bathroom, including whether there are cracks in the bathroom toilets, baths, bathtubs, toilet bowls, washbasins, etc. If there are leaks, the cracks are sometimes as fine as hairs, and you must observe carefully; Whether it is smooth, whether the sound of flushing is normal, whether the flushing water tank is leaking or not, and whether the tub, the basin and the wall or the interface of the cabinet are waterproof properly.

  

Kitchen, bathroom acceptance method three:

Whether there is a leak on the bathroom floor. Some people in the bathroom upstairs bath, downstairs toilet may be a small rain, this is because the waterproof upstairs is not done, so when the acceptance of the toilet and upstairs to coordinate, do a good job of the closed water test .

The specific acceptance method is to install sand in plastic bags upstairs and in their own toilets. All the floor drains will be completely plugged and then filled with water for 24 to 48 hours. There will be no leakage in the bathroom downstairs, indicating that there is no problem with the bathroom waterproofing. This waterproof is considered acceptable.

Kitchen, bathroom acceptance method four:

Closed water acceptance, closed water acceptance takes a long time, if the ground is found to be uneven water, all the floor tiles of the water should be knocked out, re-do the waterproof and lay the floor tiles, re-acceptance, until no water. Tip: When accepting the bathroom, do not be afraid of trouble, otherwise there will be bathroom seepage problems after entering the house, and it will be more troublesome to solve. There is a balcony with water going down and it is better to check the closed water. The most intuitive way to check the kitchen is to look at the exhaust hole first. The diameter of the exhaust hole in the kitchen is not less than 15 cm. Home life can not be separated from the kitchen, cooking a good food, natural requirements for the kitchen is relatively high. Therefore, we must be more careful when accepting the kitchen. Home life can not be separated from the kitchen, cooking a good food, natural requirements for the kitchen is relatively high. Therefore, we must be more careful when accepting the kitchen.

  

Kitchen, bathroom acceptance method five:

Observe the ventilation of the kitchen. The ventilation window area of ​​the kitchen is 1/10 of the usage area. If the kitchen room area is 10 square meters, the opening window area should be 1 square meter. In addition, the kitchen exhaust hole diameter of 15 cm, can not be installed when the hood can not be installed, it is necessary to carefully measure the acceptance.

Kitchen, bathroom acceptance method six:

In the acceptance of kitchenware, check whether the cabinet body is deformed, whether the closet door is tight and whether the door can be smoothly opened and closed; whether the kitchen utensils, tiles, and the water pipe should be carefully checked whether there is glue on the cement, whether the kitchen tile is loose or not. Shedding and bumpy, the kitchen flue need to use paper to fire smoke after the fire, placed in the mouth of the flue around 10 cm or so, see if the smoke rises to the flue mouth and immediately turn away. If everything is not a problem, the kitchen bathroom will be considered as qualified.

  

Tips: Acceptance of the kitchen must also check whether the water meter is normal. Please open the tap valve upstairs. When the water is drained, the water volume should be maximized. Then look at the water meter of your own kitchen. The water meter will not run. This indicates that the water meter is qualified because the water meter of someone's home appeared when the water in your kitchen was running. Failed to be replaced.

Construction Acceptance Toilet Decoration New House Acceptance Notice Window Housing Home Dwelling Toilet Door Cabinet Door Closet Closet Door Kitchen Cabinet Door Kitchen Bathroom Ceilings Bathroom Tiles Bathroom Doors Toilet Waterproof Bathroom Floor Tiles Toilet Leaking Kitchen Tiles Balcony Tiles